Read Mode
Time and Work
A, B, and C can do a work in 8, 14, and 16 days respectively. A works for the first 2 days. B continues and finishes two-thirds of the remaining work. C finishes the rest. How many days in total are taken to complete the work?
Correct answer: A
Explanation and memory cue
A completes 2 days of work at a rate of 1/8 per day, so completes 2/8 = 1/4 of the work. Remaining work is 3/4. B completes two-thirds of the remaining work, which is (2/3)*(3/4) = 1/2 of the total work. B's rate is 1/14 per day, so time taken by B is (1/2)/(1/14) = 7 days. Remaining work after B is 1/4. C finishes this remaining 1/4 work at a rate of 1/16 per day, so time taken by C is (1/4)/(1/16) = 4 days. Total time = 2 + 7 + 4 = 13 days. This matches option A, so the correct answer is A (13 days).