PrepSure LogoHubPage 67/182
Normal Study1,815 questions

Mathematics

Scan verified MCQs with the answer highlighted, then open explanations when you want the reasoning.

Deep Study Mode
Showing 661-670 of 1815Use Deep Study when you want one-question focus.
661

Read Mode

Time and Work

medium
Mathematics

Farjan and Kashif can complete a task in 30 days together. Farjan leaves after 20 days, and Kashif alone completes the remaining work in another 25 days. How many days does Farjan alone take to complete the entire task?

A
50
B
75
C
60
D
45
Explanation and memory cue

The problem states that Farjan and Kashif together complete the task in 30 days, so their combined work rate is 1/30 of the task per day. They work together for 20 days, completing 20/30 = 2/3 of the task. The remaining 1/3 of the task is completed by Kashif alone in 25 days, so Kashif's work rate is (1/3)/25 = 1/75 of the task per day. Farjan's work rate is the combined rate minus Kashif's rate: (1/30) - (1/75) = (5/150) - (2/150) = 3/150 = 1/50 of the task per day. Therefore, Farjan alone takes 50 days to complete the entire task. This matches option A, confirming that the correct answer is A (50).

662

Read Mode

Time And Distance

medium
Mathematics

A car traveling at 5/7 of its actual speed covers 42 km in 1 hour 40 minutes 48 seconds. What is the actual speed of the car?

A
30 km/hr
B
35 km/hr
C
25 km/hr
D
40 km/hr
Explanation and memory cue

The car covers 42 km in 1 hour 40 minutes 48 seconds at 5/7 of its actual speed. Converting the time to hours: 1 hr + 40/60 hr + 48/3600 hr = 1.68 hours. Speed at 5/7 actual speed = distance/time = 42/1.68 = 25 km/hr. Therefore, actual speed = (7/5) * 25 = 35 km/hr. However, this calculation shows 35 km/hr, matching option B. Rechecking: 1 hr 40 min 48 sec = 1 + 40/60 + 48/3600 = 1 + 0.6667 + 0.0133 = 1.68 hr. Speed = 42/1.68 = 25 km/hr (5/7 actual speed). Actual speed = (7/5)*25 = 35 km/hr. So the correct answer is B, not D. Explanation corrected accordingly.

663

Read Mode

Mensuration

medium
Mathematics

The capacity of a cylindrical tank is 246.4 litres. If the height is 4 metres, what is the diameter of the base?

A
0.14 m
B
0.28 m
C
1.4 m
D
None of these
Explanation and memory cue

The volume of the cylindrical tank is given as 246.4 litres, which converts to 0.2464 cubic meters (since 1 litre = 0.001 cubic meters). The height of the tank is 4 meters. Using the formula for the volume of a cylinder V = πr²h, we substitute the known values: 0.2464 = πr² × 4. Solving for r² gives r² = 0.2464 / (4π) ≈ 0.0196, so r ≈ 0.14 meters. The diameter is twice the radius, so diameter ≈ 0.28 meters. This matches option B. The explanation in the original question had confusing statements about decimal placement and incorrect mentions of 2.8 m, which are not relevant. The correct diameter is 0.28 m, which is option B.

664

Read Mode

Time and Work

medium
Mathematics

C takes 6 days to complete half of a work and D takes 5 days to complete one-third of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?

A
10 days
B
12 days
C
8 days
D
9 days
Explanation and memory cue

C takes 6 days to complete half the work, so C's 1 day work = 1/12 of the work. In 4 days, C completes 4 × 1/12 = 1/3 of the work. The remaining work is 2/3. D takes 5 days to complete one-third of the work, so D's 1 day work = 1/15 of the work. To complete the remaining 2/3 of the work, D needs (2/3) ÷ (1/15) = (2/3) × 15 = 10 days. Therefore, D will complete the rest of the work in 10 days, which corresponds to option A.

665

Read Mode

Time and Work

medium
Mathematics

15 men can build a 500 m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?

A
48 days
B
24 days
C
40 days
D
36 days
Explanation and memory cue

First, find the total work in man-days for the first wall: 15 men × 30 days = 450 man-days to build 500 m. The work per meter is 450 man-days / 500 m = 0.9 man-days per meter. For a 1.2 km (1200 m) wall, total work = 1200 m × 0.9 man-days/m = 1080 man-days. With 30 men working, days required = 1080 man-days / 30 men = 36 days. However, this contradicts the initial calculation, so let's re-check: 15 men × 30 days = 450 man-days for 500 m, so 1 m requires 450/500 = 0.9 man-days. For 1200 m, total man-days = 1200 × 0.9 = 1080. With 30 men, days = 1080/30 = 36 days. So the correct answer is 36 days, which corresponds to option D. The initial correction was wrong; the original correct_answer D is correct.

666

Read Mode

Time and Work

medium
Mathematics

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?

A
16
B
4
C
12
D
8
Explanation and memory cue

The total work can be calculated as 12 men × 8 hours/day × 10 days = 960 man-hours. To complete the same work in 5 days working 12 hours a day, the number of men required is 960 ÷ (12 hours/day × 5 days) = 16 men.

667

Read Mode

Time and Work

medium
Mathematics

P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they complete the job in 4 days. How many days does it take for R alone to complete the work?

A
9(3/5) days
B
9(1/5) days
C
9(2/5) days
D
10 days
Explanation and memory cue

P's work rate is 1/16 per day, Q's is 1/12 per day. Together with R, they complete the job in 4 days, so combined rate is 1/4 per day. R's rate = (1/4) - (1/16 + 1/12) = 1/4 - (3/48 + 4/48) = 1/4 - 7/48 = 12/48 - 7/48 = 5/48. Therefore, R alone takes 48/5 = 9.6 days, which is 9(3/5) days.

668

Read Mode

Time and Work

Medium
Mathematics

If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in ________?

A
1.8 days
B
1.5 days
C
1.2 days
D
1 day
Explanation and memory cue

The total work done by 6 men in 2 days is 6 × 2 = 12 man-days, which produces 10 sofas. Therefore, the man-days required to make one sofa is 12 ÷ 10 = 1.2 man-days. For 8 sofas, the total man-days required is 8 × 1.2 = 9.6 man-days. With 8 men working, the number of days required is 9.6 ÷ 8 = 1.2 days. Hence, the correct answer is 1.2 days, which corresponds to option C.

669

Read Mode

Time and Work

medium
Mathematics

P and Q can do a work in 30 days. Q and R can do the same work in 24 days, and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many more days will P take to finish the work?

A
10
B
8
C
18
D
19
Explanation and memory cue

Let the work done by P, Q, and R per day be p, q, and r respectively. From the given: p + q = 1/30, q + r = 1/24, r + p = 1/20. Adding all three: 2(p + q + r) = 1/30 + 1/24 + 1/20 = (4 + 5 + 6)/120 = 15/120 = 1/8, so p + q + r = 1/16. After 10 days working together, work done = 10 × 1/16 = 10/16 = 5/8. Remaining work = 3/8. Since Q and R left, only P works now at rate p = (p + q + r) - (q + r) = 1/16 - 1/24 = (3 - 2)/48 = 1/48 per day. Time for P to finish remaining work = (3/8) ÷ (1/48) = 18 days. However, the calculation shows 18 days, but the options have 8 as B and 18 as C. Rechecking: p = (p + q + r) - (q + r) = 1/16 - 1/24 = (3/48 - 2/48) = 1/48. Remaining work = 3/8. Time = (3/8) / (1/48) = (3/8) × 48 = 18 days. So correct answer is C (18). The original answer was correct. The explanation was missing and difficulty was not set; difficulty is medium. Tags added for clarity.

670

Read Mode

Time and Work

medium
Mathematics

10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?

A
7
B
5
C
6
D
4
Explanation and memory cue

Given: 10 men can complete the work in 7 days, so the work done by 10 men in 1 day is 1/7. Therefore, work done by 1 man in 1 day is (1/7)/10 = 1/70. Similarly, 10 women can complete the work in 14 days, so work done by 10 women in 1 day is 1/14. Therefore, work done by 1 woman in 1 day is (1/14)/10 = 1/140. Now, work done by 5 men in 1 day = 5 × (1/70) = 1/14. Work done by 10 women in 1 day = 10 × (1/140) = 1/14. Total work done by 5 men and 10 women in 1 day = 1/14 + 1/14 = 1/7. Hence, the total number of days required to complete the work = 1 / (1/7) = 7 days. Therefore, the correct answer is 7 days, which corresponds to option A.