A and B can do a piece of work in 21 and 24 days respectively. They start the work together, and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?
Correct answer: C
Explanation and memory cue
A's work rate is 1/21 per day and B's work rate is 1/24 per day. B works alone for 9 days, completing 9/24 = 3/8 of the work. Therefore, A and B together completed 5/8 of the work before A left. Their combined work rate is 1/21 + 1/24 = 45/504 per day. The time they worked together is (5/8) ÷ (45/504) = (5/8) × (504/45) = 7 days. Hence, A left after 7 days, which corresponds to option C.